What type of chart graphs the starting and finishing times for individual tasks in a project?

  1. Gantt Chart

  2. Pie Chart

  3. Line Chart

  4. Bar Chart

The correct answer is: Gantt Chart

A Gantt Chart is specifically designed to illustrate the schedule of a project by displaying the starting and finishing times for individual tasks or activities. This visual representation allows project managers and teams to see the duration of each task, the sequence in which they occur, and any overlaps between tasks. By providing a clear timeline, a Gantt Chart helps in tracking progress and ensuring that project deadlines are met. Other types of charts, such as pie charts, line charts, and bar charts, serve different purposes. Pie charts are typically used to represent parts of a whole or percentages, line charts are great for showing trends over time with continuous data, and bar charts are effective for comparing quantities across categories. However, none of these chart types convey the timeline and duration of project tasks in the detailed manner that a Gantt Chart does. Thus, the Gantt Chart is the most suitable option for this specific need in project management.