Prepare for the Contractor License Exam with comprehensive quizzes. Study with multiple choice questions, flashcards, and detailed explanations to ensure you're ready for success on exam day!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is NOT a step involved in closing out a project?

  1. Onsite walk-through to develop a punch list

  2. Subcontractor review meeting

  3. Owner makes final payment

  4. Contractor/architect provide certificate

The correct answer is: Subcontractor review meeting

The process of closing out a project involves several key steps that ensure that all aspects of the project are completed and finalized. A subcontractor review meeting typically occurs during the project implementation phase rather than during the closing phase. This meeting allows for assessing work done by subcontractors, discussing performance, and addressing any issues that arose during construction. In contrast, an onsite walk-through to develop a punch list is a crucial part of project closure. This step involves inspecting the completed work to identify any outstanding tasks or deficiencies that need to be addressed before finalizing the project. Similarly, the owner making the final payment signifies that the project is completed to their satisfaction, marking the official end of the project. The contractor and architect providing a certificate of completion is also a key closing procedure that confirms all contractual obligations have been met. Therefore, while the subcontractor review meeting is important for project management, it falls outside the closure activities, making it the correct answer in this context.