Prepare for the Contractor License Exam with comprehensive quizzes. Study with multiple choice questions, flashcards, and detailed explanations to ensure you're ready for success on exam day!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which statement is NOT true about project scheduling?

  1. Project schedules are only required on major projects.

  2. Project schedules help in efficient resource management.

  3. Most projects require a timeline to be successful.

  4. Schedules can change based on project needs.

The correct answer is: Project schedules are only required on major projects.

The statement that project schedules are only required on major projects is not true. In reality, project scheduling is essential for projects of all sizes, not just the major ones. Even small projects benefit from having a schedule because it allows for better organization, task prioritization, and time management. Schedules provide clarity on deadlines and help in tracking progress, ensuring that even minor tasks are completed efficiently. The other statements highlight critical aspects of project scheduling. For instance, schedules help in efficient resource management by allocating time and resources effectively across different tasks. Additionally, the necessity of a timeline is prevalent in most projects, as it serves as a framework for achieving objectives within a specified period. Finally, flexibility in scheduling is important, as project needs may evolve over time, necessitating adjustments to the original plan.